Museum of Contemporary Art
Los Angeles, CA

Award Winning Energy Efficiency Project

PROJECT BACKGROUND

The Museum of Contemporary Art (MOCA) in Downtown Los Angeles houses nearly 5,000 artworks created since 1940, including classic and new masterpieces by contemporary artists. MOCA’s best-in-class 2018 energy project more than halved energy use at the facility. This project was prompted by an Energy Assessment conducted by ABM, which recommended as Engine Control Modules (ECMs) air handler and controls renovations.

PROJECT REQUIREMENTS

  • Supply Fan Blower Section – New Blower Motor, New stainless steel interior, New AstroFoil insulation (South Gallery)
  • New Blower Motor, New epoxy coat paint, New AstroFoil insulation (auditorium)
  • New AstroFoil insulation (Galleries C, D, & E)
  • New insulated copper piping and New Paint (Library Air Handler)
  • Air Handler Humidification – High-Pressure MeeFog Atomizing Nozzles
  • New copper cooling coils
  • New sheet metal dampers with new DDC Motors
  • New VFDs were installed to control supply and exhaust fans

WHAT SUNBELT CONTROLS DELIVERED

The original scope of work called for the rental of temporary chillers, air handlers and humidifiers, along with piping, to be located on a flat-bed on lower Grand Avenue just outside the museum. This would provide heating, cooling and humidification to each gallery while its air handling unit (AHU) was ‘down’ for refurbishment. The cost of this rental was $128,000.00. The design engineer and ACCO thought there might be overcapacity in the AHU’s, due to skylights being boarded over, changing of lamps to LED’s (75w-17w), and general oversizing of the equipment in the original design. Together, we devised a plan to share the load of a single AHU across two galleries.

Tests were conducted to determine how long the Galleries could maintain temperature and humidity. The tests showed that the galleries could maintain design conditions for up to 6 hours without AC. Flexible ductwork was connected from one air handler to serve two separate galleries while repairs and upgrades were performed on the second air handler. This process continued until all (10) air handlers were cut over. For Sunbelt Controls, programing was involved and fine-tuning the PID loops took some time. Once each one was tuned, the units were able to maintain the conditioned space set-points with very little deviation and effort. ALC Controls was able to utilize significantly less energy than originally predicted in the ECM and exceed saving results in just 6 months.

After the project was completed, MOCA won the 2018 U.S. Department of Energy’s Los Angeles Better Building Challenge (LABBC) Innovation Award for Energy Efficiency. This award recognizes a building that has achieved the greatest annual reduction in energy use or that has demonstrated the greatest continued improvement over time. 6 months following the completion of the project, MOCA had reduced its electrical consumption by more than 50%.

Project Team

OWNER: Museum of Contemporary Art

ARCHITECT: Arata Isozaki

MECHANICAL ENGINEER: ACCO Engineered Systems

CONTROLS CONTRACTOR: Sunbelt Controls